Owner: Thai Oil
Contractor: UJV (Petrofac, Saipem, Samsung)
Project: Clean Fuel Project
Project Location: Siracha, Chonburi
Duration: August 2020 - April 2022
Scope of Work:
- PAR/PAS Module Fabrication & Erection/ SMP Works
- Steel Structure Fabrication - 1,700T
- Structure Erection - 6,000T
- Equipment Erection - 12,843T
- Piping Fabrication - 30,821 Di
- Piping Erection - 164,000Di